KDP was established in Jakarta 24 October 2000 as an Indonesian Domestic Private Company.
The first project was Rental of Construction Equipment for Central Gathering Station Chevron
Pacific Indonesia and as
Chiyoda’s Subcontractor for PGR Project PT. Badak NGL Bontang.
2001
BPPT for Inverter Supply for BPPT Building (Mechanical & Electrical), Jakarta.
IKPT for Warehouse Renovation, Tambun-Bekasi.
2002
BHP Steel for Piping, Steel, Civil, Mechanical & Installation work BSI Pain Line Upgrade
project, Cilegon-Banten.
IKPT-KBR for Housing Renovation Sintuk II – Bontang Kaltim.
2004
PT WIKA - Adhi Karya - IKPT, Aromatic Tuban for: Civil Work Package II.
PT Kelsri for Aromatic Tuban-TPPI, Piping Work Fabrication and Installation.
PT. Karya Internusa for Steel Erection in Kujang 1B Cikampek.
PT Hutama Karya for Kujang 1B: Bridge Strengthening work Kalisadang & Cikarang
PT. SAS Intern’l for Flare Gas & Hydrogen Recovery Pertamina RU V Balikpapan for Piping, Steel,
Civil, Mechanical &
Installation Work.
Chiyoda’s Subcontractor for Betara Complex Development PetroChina for Ready Mix Concrete and
Scaffolding, in Jambi.
2005
Pertamina PPGS South Sumatra as IKPT’S Subcontractor for: 14”: Gas Pipeline Merbau-Pagardewa 23
KM and Engineering
Services.
2006
PT Pertamina EP PPGS South Sumatra as IKPT’S Subcontractor for: Mechanical Installation &
Mechanical Work.
2007
Amerada Hess, Gresik as IKPT’s Subcontractor for Steel Structure Erection.
PT Chandra Asri Petrochemical Revamping Project as IKPT’s Subcontractor for Steel Structure
Erection.
PT Perusahaan Gas Negara Project , with KSO Moeladi - Adhi Karya - Krakatau Engineering for 24”
Gas Pipeline 34 Km
Rawamaju-Walahar for Proyek Pengembangan Jaringan Pipa Gas Bumi JABAR
Chiyoda Corp for Propane Dryer & Shutdown.
2008
PT Krakatau Engineering Subcontractor for 20” Gas Pipeline Installation, Cilegon-Banten.
PT TPPI , TTU Tuban Project as IKPT Subcontractor for Civil Work, Civil & Steel Work, Mechanical
Equipment.
2009
PT Petrokimia Gresik for Pipeline 28” Babat-Gresik Stage IX Relocation & Recondition.
2010
PT. MNK Indonesia, IKPT’ Subcontractor for Piping underground and aboveground.
2012
PT PERTAMINA EP , Central Processing Plant (CPP) Area Gundih, IKPT - Adhi Karya Subcontractor
for Piping Work
2013
PT JGC Indonesia Subcontractor for: JCF Plant Modification, Karawang West Java for Structure
Work.
2014
JGC Indonesia Subcontractor for: Plant site of PT. JCF (JCF Coal Fuel) Karawang West Java for
Work
Package: Mechanical,
Piping, Insulation and Painting Work
JGC Indonesia Subcontractor for: Shell LOBP Monas, Marunda Bekasi for Mechanical Erection Work:
Rotary Machine,
Equipment Package, ABB Package equipment for Blending, Boiler Package, Static Equipment such as
pressure vessel, shop
fabrication tank, suction heater, EDG.
2019
New Polyethylene Reactor Line Project New Swing Plant Of HOPE, LLDPE AND MLLDPE, PT Chandra Asri
Petrochemical Cilegon,
IKPT-TOYO Subcontractor for
Support Steel Structure and Painting Works
Support Piping Works Task Force Team To Support Piping Works
Rental of Air Compressor 1600 CFM Supply Manpower for Mechanical Task Force
PT. Synthetic Rubber Indonesia, Cilegon Banten for Repair slurry tank and piping fabrication and
modification
PT. Chandra Asri Indonesia, Contractor for Turn Around of PT CAP
PT. Petrokimia Butadine Indonesia , IKPT’s Subcontractor for B1MTBE & EGF project for Piping
work
PT GEODIPA ENERGY - DIENG, IKPT’s Subcontractor for Temporary Facilities
2020
PT. Chandra Asri Indonesia, IKPT’ Subcontractor for NPE shutdown activity.
PT. Nippon shokubai Indonesia , IKPT’s Subcontractor for i-III project .
PT. Nippon shokubai Indonesia , Rental of Workshop, Heavy Equipment, Genset & Welding machine,
Office & Warehouse
Container
2021
PT. Hutama Karya
Subcontractor DED Services
HAZOP dan HAZID Study ,
Open Access RU-VII KASIM –
PAPUA
PT. SYNTHETIC RUBBER INDONESIA. Butadine By-Pass Facility – BEST CONTRACTOR 2021.
PT. LINDE INDONESIA. Evaporator Line, By-Pass Valve, Modif. Valve & Repair crack join, Lift
dismantling.
PT. SYNTHETIC RUBBER INDONESIA. Butadine Column Antipop Improvement
PT. SYNTHETIC RUBBER INDONESIA. Recycle Acid Waste Project
PT. Chandra Asri Indonesia, IKPT Equip’t, Materials supply, Manpower and equip’t for Turn Around
& Maintenance PP
PT. SMELTING / IKPT, Tempfac for Sulfuric Acid.
2022
PT. SYNTHETIC RUBBER INDONESIA. Dry Seal Evolution
PT. SRI. DUPLEX-2 Stripping Spool Material Supply
PT. LINDE INDONESIA. Piping work, Platform, Handrail Maintenance,
PT. SRI DUPLEX-2 Stripping Fabrication & Installation – QUALITY AWARD 2022.
PT. SRI Stripping DUPLEX-3 Fitting Material Supply